Skip to main content
 
Assessing Mobile Technologies in Child Protective Services



Chapter 4: Productivity and Efficiency

Timeliness

One indicator of timeliness used is elapsed time – or the number of days between an event and the posting of documentation in the CONNETIONS system regarding that event, or the length of time necessary to close a case. If we look at the age of cases, for only those cases that opened and closed within the pre-pilot period (April 28, 2007 – July 20, 2007) and the during-pilot period (July 30, 2007 – October 19, 2007), we see a picture which demonstrates timeliness increases. The trend line during the pilot shows a marked increase in cases closed within approximately the first seven days and the percentage of cases closed is higher overall by approximately 10 % over the pre-pilot figures. The pre-pilot trend line also shows a steep increase as it nears 60 days and this may represent CPS workers playing “catch-up” in order to meet the required time frames. With the technology, the days approaching 60 days is much smoother and reflects less of an accelerated “catching-up” process.

Graph 8 - Age of Cases When Closed

Graph  8  - Age of Cases When Closed

Table 2 below represents the percentage of safety assessments submitted over a seven day period. Very few safety assessments are submitted on the same day the cases investigation opens. This is as expected given that completing a safety assessment requires multiple tasks to be completed, such as visiting the home and contacting individuals. Three-quarters of the safety assessments (74 % pre- and 74 % during) are submitted by day seven for both the pre- and during-pilot periods.

Table 2- Percentage of Safety Assessments Submitted Within 7 Days

 
Same day
4 days
1 day
5 days
2 days
6 days
3 days
7 days
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
Percent of all safety assessments submitted
 
.09
 
.14
 
3.
 
2
 
8
 
9
 
15
 
17
 
Number of safety assessments
 
1
 
1
 
31
 
17
 
55
 
45
 
76
 
63
 
 
Same day
4 days
1 day
5 days
2 days
6 days
3 days
7 days
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
Percent of all safety assessments submitted
 
24
 
27
 
35
 
38
 
52
 
53
 
74
 
74
 
Number of safety assessments
 
95
 
67
 
116
 
86
 
182
 
109
 
230
 
152
 

With 75 % of safety assessments submitted by day seven, that leaves 25 % for improvement and a chance for some technological impact. However, 95 % of all safety assessments are submitted by day 14 after the start of a case (95.2 % pre-pilot period; 95.6 % during-pilot period). Too many factors may be at play here to expect the technology alone to improve timeliness, including tracking down clients or waiting for information from other parties.

We also looked at the elapsed time between progress note entry and the related event. During both periods, approximately half of all progress notes are entered on the same day as the event, and approximately two-thirds are entered within one day after the event. In addition, three-quarters of all progress notes are entered by three-days after the event. We would have expected the proportion of notes on the same day, next day, and second day to increase from the pre-pilot periods. However, there were not overall increases in the proportion, indicating no productivity gains in the reporting process. In addition, if three-days is considered contemporaneous, that leaves only 25 % of all notes where technology impacts may help to improve timeliness.

Table 3- Percentage of Notes Submitted Within 5 Days

 
Same day
3 days
1 day
4 days
2 days
5 days
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
% of all notes entered
 
50
 
50
 
66
 
65
 
71
 
70
 
Number of notes entered
 
10348
 
8608
 
3469
 
2713
 
1047
 
890
 
 
Same day
3 days
1 day
4 days
2 days
5 days
Pre
 
During
 
Pre
 
During
 
Pre
 
During
 
% of all notes entered
 
76
 
75
 
80.
 
79
 
83
 
83
 
Number of notes entered
 
1085
 
884
 
792
 
657
 
591
 
586
 

There are some slight differences between field offices with Manhattan more able to get progress notes in by the first day, but Staten Island testers catch up by day two. In Manhattan, about half of all progress notes were entered on the same day before and during the pilot (52 % pre-pilot; 51 % during-pilot) and about two-thirds were entered one day after the event (68 % pre-pilot; 65 % during-pilot). In Staten Island, about half of all progress notes were entered on the same day (47 % pre-pilot; 49 % during-pilot) and almost two-thirds were entered one day after the event (69 % pre-pilot; 65 % during-pilot).

Graph 9 focuses on elapsed time and plots the percentage of all notes entered by days from the note entry to related event for each field office. Overall, the same pattern is present as above – no substantial technology impacts on timeliness of progress notes is apparent for each field office.

The information we gathered from surveys and workshops may shed some light on these patterns. First, timeliness is impacted by individual work styles and caseloads. Some individuals were very timely before the introduction of technology, and some were not. Some supervisors reported seeing substantial improvements in productivity in some testers. The introduction of technology appears to affect individuals differently and the aggregate results are that modest gains by one person is adjusted by modest losses for another person. One caseworker stated, “Even though the laptop makes case notes entry a lot easier, because I am able to access CONNECTIONS from anywhere, as long as a signal is available, there is still the issue of the caseload size as well as some of the individual cases and the type of family and their issues that we have to deal with.”

Graph 9 - Percent of Notes Entered by Day After Event by Field Office

Graph  9  - Percent of Notes Entered by Day After Event by Field Office

CPS workers in the workshops described working with their supervisors to close a case while the worker was in the field, and being able to enter the information the supervisor needed to close the case. While, changing overall work habits may not happen in a 12-week pilot test, these experiences represent positive work changes.