Constructing the New York State-Local Internet Gateway Prototype: A Technical View



Methodology and Timeline

Table 2. Time Period, Participants, Actions, and Products and Results

Time Period
 
Participants
 
Actions
 
Products and Results
 
Project Exploration and Initiation
Summer 2002
 
  • NYS Office For Technology’s Local eCommerce/ eGovernment Advisory Committee
 
  • Committee meetings and workshops
 
  • Discussions about the growing number of individual intergovernmental information systems and ideas about pursuing single point of contact
 
Fall 2002
 
  • CTG
  • Members of NYS OFT’s Local eCommerce/ eGovernment Advisory Committee
 
  • Exploratory meetings and workshops
 
  • Current practice research
  • Identification of characteristics of an ideal state-local gateway
  • Identification of applications for the Prototype
  • Recruitment of Prototype Team Members
 
Systems Analysis, Design, & Development
Winter 2003
 
  • CTG
  • Prototype Team members
 
  • Prototype development meetings
 
  • Detailed end-to-end process maps
  • Prototype scope statements
  • Application-specific service objective statements
 
Summer 2003
 
  • Corporate Partners
  • CTG
  • Prototype Team members
 
  • Joint Application Development (JAD) sessions
 
  • Functional requirements
  • Business process rules
  • Data flows and requirements
 
Fall 2003
 
  • Corporate Partners
  • CTG
  • Prototype Team members
 
  • Development meetings
  • Writing, testing software
  • Code and Design review
 
  • Web maps
  • Software architecture documents
  • Software requirement specifications
  • Use case realization specifications
  • Source data identification
  • Data cleansing and integration
  • Draft Prototype components
 
Testing
Fall 2003
 
  • Corporate Partners
  • CTG
  • Prototype Team members
 
  • Individual application testing
  • Integration testing
  • User acceptance testing
 
  • Refined Prototype ready for field test
 
Training and Prototype Evaluation
Fall 2003
 
  • Corporate Partners
  • CTG
  • Prototype Team members
  • Additional Field Testers
 
  • Training
  • 2-week Field Test
  • Discussion groups
 
  • Prototype Evaluation
  • Project Report
 
Prototype Decommission
Late Fall 2003
 
  • Corporate Partners
  • CTG
 
  • Prototype debrief session
  • Prototype disabled
 
  • Documented learning from Prototype development
  • Prototype artifacts archived